20 Mar 2025

11:35 Asian Stanley. International Limited 4.00 hours (Project progress work #786 (Closed): [Colding] Handy terminal BT-A500 Java application [Label printing system (Taping)])
test and fix bug in api (step taping check) Soraya Norasing
11:26 Asian Stanley. International Limited 4.00 hours (Project progress work #786 (Closed): [Colding] Handy terminal BT-A500 Java application [Label printing system (Taping)])
add printer to server , setup printer, support user online Soraya Norasing
11:18 Asian Stanley. International Limited 3.00 hours (Project progress work #786 (Closed): [Colding] Handy terminal BT-A500 Java application [Label printing system (Taping)])
test windows app with K.fight Soraya Norasing
10:47 Asian Stanley. International Limited 8.00 hours (Project progress work #786 (Closed): [Colding] Handy terminal BT-A500 Java application [Label printing system (Taping)])
Install update & support user on site Soraya Norasing
11:33 Asian Stanley. International Limited 4.00 hours (Project progress work #784 (Closed): [Colding] Handy terminal BT-A500 Java application (Process Control System))
test and fix bug (bonding check process can't scan machine) Soraya Norasing
11:27 Tomas Tech Co.,Ltd. 8.00 hours (Project progress work #622 (In Progress): For internal meeting and other)
meeting at NTPT about asprova Soraya Norasing
11:24 Asian Stanley. International Limited 1.00 hour (Project progress work #788 (Closed): [Colding] Handy terminal BT-A500 Java application [Label printing classify rank system])
meeting online get requirement with customer Soraya Norasing
11:19 Asian Stanley. International Limited 5.00 hours (Project progress work #788 (Closed): [Colding] Handy terminal BT-A500 Java application [Label printing classify rank system])
prepare spec doc Soraya Norasing
11:23 Asian Stanley. International Limited 3.00 hours (Project progress work #790 (Closed): [Colding] Handy terminal BT-A500 Java application [Calling maintenance staff system])
meeting with customer get requirement Soraya Norasing
11:20 YAMATO ELECTRIC (THAILAND) CO.,LTD 8.00 hours (Project progress work #797 (Close request): [Installation] HT_YDT WMS)
support user onsite Soraya Norasing
11:20 YAMATO ELECTRIC (THAILAND) CO.,LTD 8.00 hours (Project progress work #797 (Close request): [Installation] HT_YDT WMS)
support user onsite Soraya Norasing
 