Priroj Neamjarn's activity
From 20 Feb 2025 to 01 Mar 2025
01 Mar 2025
- 17:22 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- -Coding Stock management process
- 17:22 PT NIPPON KONPO INDONESIA Project progress work #895: [Cording] Warehouse management system for NKI Handy Java
- today
-Coding Stock management process
tomorrow
-Coding Stock management process - 17:22 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- -Coding Stock management process
28 Feb 2025
- 17:10 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- -Coding Stock management process
- 17:10 PT NIPPON KONPO INDONESIA Project progress work #895: [Cording] Warehouse management system for NKI Handy Java
- today
-Coding Stock management process
tomorrow
-Coding Stock management process - 17:10 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- -Coding Stock management process
27 Feb 2025
- 17:18 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- -Coding Stock management process
- 17:18 PT NIPPON KONPO INDONESIA Project progress work #895: [Cording] Warehouse management system for NKI Handy Java
- today
-Coding Stock management process
tomorrow
-Coding Stock management process - 17:18 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- -Coding Stock management process
26 Feb 2025
- 17:07 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- -Coding Inbound Rack process
- 17:07 PT NIPPON KONPO INDONESIA Project progress work #895: [Cording] Warehouse management system for NKI Handy Java
- today
-Coding Inbound Rack process
tomorrow
-Coding Inbound Rack process
-Coding Outbound process
- 17:07 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- -Coding Inbound Rack process
21 Feb 2025
- 18:10 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- -Coding Inbound QC process
- 18:10 PT NIPPON KONPO INDONESIA Project progress work #895: [Cording] Warehouse management system for NKI Handy Java
- today
-Coding Inbound QC process
tomorrow
-Coding Inbound QC process
-Coding Inbound Rack process - 18:10 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- -Coding Inbound QC process
20 Feb 2025
- 17:56 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- Coding Inbound QC process
- 17:56 PT NIPPON KONPO INDONESIA Project progress work #895: [Cording] Warehouse management system for NKI Handy Java
- today
-Coding Inbound QC process
tomorrow
-Coding Inbound QC process
-Coding Inbound Rack process - 17:56 PT NIPPON KONPO INDONESIA 8.00 hours (Project progress work #895 (Closed): [Cording] Warehouse management system for NKI Handy Java)
- Coding Inbound QC process
Also available in: Atom