06 Feb 2025

22:34 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #782 (Closed): [Colding] Web application Android)
Install 4/5 Priroj Neamjarn
22:34 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #782: [Colding] Web application Android
Install 4/5 Priroj Neamjarn
22:34 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #782 (Closed): [Colding] Web application Android)
Install 4/5 Priroj Neamjarn

05 Feb 2025

17:59 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #782 (Closed): [Colding] Web application Android)
Install 3/5 Priroj Neamjarn
17:57 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #782: [Colding] Web application Android
Install 3/5 Priroj Neamjarn
17:57 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #782 (Closed): [Colding] Web application Android)
Install 3/5 Priroj Neamjarn

04 Feb 2025

21:32 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #782 (Closed): [Colding] Web application Android)
Install 2/5 Priroj Neamjarn
21:32 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #782: [Colding] Web application Android
Install 2/5 Priroj Neamjarn
21:32 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #782 (Closed): [Colding] Web application Android)
Install 2/5 Priroj Neamjarn

03 Feb 2025

16:35 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #782 (Closed): [Colding] Web application Android)
Install 1/5 Priroj Neamjarn
16:35 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #782: [Colding] Web application Android
Install 1/5 Priroj Neamjarn
16:35 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #782 (Closed): [Colding] Web application Android)
Install 1/5 Priroj Neamjarn

01 Feb 2025

22:06 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #782 (Closed): [Colding] Web application Android)
-final test Priroj Neamjarn
22:06 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #782 (Confirmation request): [Colding] Web application Android
today
-final test
Priroj Neamjarn
22:06 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #782 (Closed): [Colding] Web application Android)
-final test Priroj Neamjarn
22:04 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #829 (Closed): [Colding] C# linkage application of AS400)
-final test Priroj Neamjarn
22:04 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #829 (Confirmation request): [Colding] C# linkage application of AS400
today
-final test
Priroj Neamjarn
22:04 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #829 (Closed): [Colding] C# linkage application of AS400)
-final test Priroj Neamjarn

31 Jan 2025

17:18 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #829 (Closed): [Colding] C# linkage application of AS400)
-Unit test -fix bug linkage Priroj Neamjarn
17:17 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #829: [Colding] C# linkage application of AS400
today
-Unit test
-fix bug linkage
tomorrow
-Unit test
-fix bug linkage
-fix bug handy
Priroj Neamjarn
17:17 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #829 (Closed): [Colding] C# linkage application of AS400)
-Unit test -fix bug linkage Priroj Neamjarn
 