20 Jan 2025
- 18:56 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Update Setup/Vanning Process
-Update QGate Process
18 Jan 2025
- 16:44 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Adjust Setup/Vanning Process
17 Jan 2025
- 18:54 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-install the application.
16 Jan 2025
- 16:47 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #782: [Colding] Web application Android
- today
-NG Manual
-Transfer in process
tomorrow
-NG Manual
-Transfer in process - 16:44 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-install the application.
15 Jan 2025
- 17:08 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #782: [Colding] Web application Android
- today
-NG Manual
-Transfer in process
tomorrow
-NG Manual
-Transfer in process - 16:46 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-install the application.
14 Jan 2025
- 16:38 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-install the application.
13 Jan 2025
- 16:59 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-install the application.