26 Dec 2024

10:09 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #849 (Closed): EE Drawing deisgn)
Drawing EE and PO Phatthadon Inthachot
10:08 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #849 (Closed): EE Drawing deisgn)
Drawing EE and PO Phatthadon Inthachot
10:03 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #849 (Closed): EE Drawing deisgn)
Drawing EE Phatthadon Inthachot
10:02 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #849 (Closed): EE Drawing deisgn)
Drawing EE Phatthadon Inthachot
10:02 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #849 (Closed): EE Drawing deisgn)
Drawing EE Phatthadon Inthachot
09:30 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #849 (Closed): EE Drawing deisgn)
Drawing EE Phatthadon Inthachot
09:30 NTN MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #849 (Closed): EE Drawing deisgn)
Drawing EE Phatthadon Inthachot
10:07 ADVICS MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #835 (Closed): EE Drawing deisgn)
Drawing EE Phatthadon Inthachot
10:07 ADVICS MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #835 (Closed): EE Drawing deisgn)
Drawing EE Phatthadon Inthachot
10:07 ADVICS MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #835 (Closed): EE Drawing deisgn)
Drawing EE Phatthadon Inthachot
10:06 ADVICS MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #835 (Closed): EE Drawing deisgn)
Drawing EE Phatthadon Inthachot
10:05 ADVICS MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #835 (Closed): EE Drawing deisgn)
Drawing EE and PR Phatthadon Inthachot
10:04 ADVICS MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #835 (Closed): EE Drawing deisgn)
Drawing EE and PR Phatthadon Inthachot
09:28 TOMAS TECH CO., LTD. 8.00 hours (Sales support #798 (New): Site survey customer for new project)
Check control panel of PJ Taceability system AS004 for ADVICS Phatthadon Inthachot
09:06 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #806 (New): Estimate cost)
Drawing EE signal I/O for AHT CNC Phatthadon Inthachot
09:00 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #806 (New): Estimate cost)
Drawing EE signal I/O for AHT CNC Phatthadon Inthachot
08:37 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #806 (New): Estimate cost)
Drawing Layout control panel Phatthadon Inthachot
08:54 KEYENCE (THAILAND) CO., LTD. 8.00 hours (Project progress work #875 (Closed): Assy and Wiring)
test power on and program Phatthadon Inthachot
08:53 KEYENCE (THAILAND) CO., LTD. 8.00 hours (Project progress work #875 (Closed): Assy and Wiring)
Wiring cabinet Phatthadon Inthachot
08:33 KEYENCE (THAILAND) CO., LTD. 8.00 hours (Project progress work #875 (Closed): Assy and Wiring)
Wiring cabinet Phatthadon Inthachot
08:33 KEYENCE (THAILAND) CO., LTD. 8.00 hours (Project progress work #875 (Closed): Assy and Wiring)
Assy and Wiring Phatthadon Inthachot
08:50 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #523 (New): Phatthadon Inthachot Taking Day off January-December 2024)
Day off Phatthadon Inthachot
08:46 OTICS (THAILAND) CO., LTD. 8.00 hours (Project progress work #876 (Closed): Check Power meter)
Check Power meter Phatthadon Inthachot
08:46 OTICS (THAILAND) CO., LTD. 8.00 hours (Project progress work #876 (Closed): Check Power meter)
Check Power meter Phatthadon Inthachot
08:46 OTICS (THAILAND) CO., LTD. 8.00 hours (Project progress work #876 (Closed): Check Power meter)
Check Power meter Phatthadon Inthachot
08:46 OTICS (THAILAND) CO., LTD. 8.00 hours (Project progress work #876 (Closed): Check Power meter)
Check Power meter Phatthadon Inthachot
08:36 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #801 (Closed): EKD system phase 4)
Setup Camera Phatthadon Inthachot
08:36 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #801 (Closed): EKD system phase 4)
Setup Camera Phatthadon Inthachot
08:29 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #729 (Closed): [ Installation & On-site support] Hardware installation for IoT Loss analysis MOC and Packing process Line 1,2)
Support installation Phatthadon Inthachot
08:27 DAIFUKU (THAILAND) LTD. 8.00 hours (Project progress work #800 (Closed): [Area1] Camera control system)
Wiring cabinet Phatthadon Inthachot
 