Priroj Neamjarn's activity
From 02 Dec 2024 to 11 Dec 2024
11 Dec 2024
- 16:28 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- coding Q-Gate process
- 16:28 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-create screen Q-Gate for Handy
-create screen Q-Gate for Tablet
-create Socket API
tomorrow
-create scree... - 16:28 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- coding Q-Gate process
10 Dec 2024
- 16:22 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #829 (Closed): [Colding] C# linkage application of AS400)
- create stored procedure, create trigger
- 16:21 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #829: [Colding] C# linkage application of AS400
- today
-create stored procedure
-create trigger
-adjust linkage data windows application
tomorrow
-adjust linkage... - 16:21 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #829 (Closed): [Colding] C# linkage application of AS400)
- create stored procedure, create trigger
09 Dec 2024
- 16:39 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #829 (Closed): [Colding] C# linkage application of AS400)
- create stored procedure, trigger
- 16:39 MINEBEA ACCESSSOLUTIONS THAI LTD. Project progress work #829 (In Progress): [Colding] C# linkage application of AS400
- today
-create stored procedure
-create trigger
tomorrow
-create stored procedure
-create trigger
-adjust linkag... - 16:39 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #829 (Closed): [Colding] C# linkage application of AS400)
- create stored procedure, trigger
06 Dec 2024
- 16:26 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Internal test case
- 16:25 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Internal test case
tomorrow
-Dashboard
-Q-Gate (new requirement) - 16:25 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Internal test case
04 Dec 2024
- 16:36 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Adjust the power meter calculation function of OTIC.
- 16:36 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Adjust the power meter calculation function of OTIC.
tomorrow
-Adjust the power meter calculation function ... - 16:36 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Adjust the power meter calculation function of OTIC.
03 Dec 2024
- 16:57 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Adjust the power meter calculation function of OTIC.
- 16:57 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Adjust the power meter calculation function of OTIC.
-Meeting to discuss the specifications of the Stock ma... - 16:57 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Adjust the power meter calculation function of OTIC.
02 Dec 2024
- 16:34 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Packing monthly summary report
- 16:34 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Packing monthly summary report
-Dashboard
tomorrow
-Dashboard - 16:34 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #739 (Closed): [Development] CKD process system phase4 )
- Packing monthly summary report
Also available in: Atom