Nattapol Poeam's activity
From 01 Dec 2024 to 10 Dec 2024
09 Dec 2024
- 10:25 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work #858 (Closed): [ Installation & On-site support] Program PLC Installation Pintong
- - Program installation
- 10:24 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work #857 (Closed): [ Installation & On-site support] Program PLC Installation Soi6
- - Program installation & connect to Power meter
- 10:22 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work #856 (Closed): [ Installation & On-site support] Program PLC Installation Soi3
- - Program PLC Installation & Power connection
- 10:12 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work #855 (Closed): [ Installation & On-site support] Control box installation #Pintong
- - Control box installation and connect system
- 10:11 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work #854 (Closed): [ Installation & On-site support] Control box installation #Soi6
- - Control box installation and connect system
- 10:07 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work #853 (Closed): [ Installation & On-site support] Control box installation #Soi3
- - Control box installation and connect system
- 09:42 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work #852 (Closed): [ Installation & On-site support] Software installation PLC
- Program installation and testing
1. Soi 3
2. Soi 6
3. Pinthong - 09:39 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work #851 (Closed): [ Coding ] Program development PLC
- - Make function power meter pulling
- 08:52 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work #850 (Closed): Power Meter Parameter check
- 1.Check parameter power meter SOI 3,SOI 6,PINTONG
1.1 IP Address from MOXA ( Ethernet converter )
1.2 Meter Node I... - 08:49 NTN MANUFACTURING (THAILAND) CO., LTD. Project progress work #849 (Closed): EE Drawing deisgn
- - Make drawing EE
- Summary equipment
03 Dec 2024
- 11:11 ADVICS MANUFACTURING (THAILAND) CO., LTD. Project progress work #842 (Closed): HW Onsite installation
- 1. Installation PLC Master
2. Installation HMI
3. Installation PC
4. Installation Table
5. Setup equipment - 11:10 ADVICS MANUFACTURING (THAILAND) CO., LTD. Project progress work #841 (Closed): Table installation
- - Table installation and setup
- 11:08 ADVICS MANUFACTURING (THAILAND) CO., LTD. Project progress work #840 (Closed): Connect to machine
- Connect CC-Link system to Machine
OP1
OP4
OP6
OP7.1
OP7.2
OP8
OP9
OP10.1
OP10.2 - 11:05 ADVICS MANUFACTURING (THAILAND) CO., LTD. Project progress work #839 (Closed): Software external installation
- - Installation Program PLC
- Installation Program C# Application - 11:02 ADVICS MANUFACTURING (THAILAND) CO., LTD. Project progress work #838 (Closed): Specification design
- - Make specification for traceability AS004
- 10:59 ADVICS MANUFACTURING (THAILAND) CO., LTD. Project progress work #837 (Closed): ME Assembly [ Table ]
- - Assembly table
- 10:58 ADVICS MANUFACTURING (THAILAND) CO., LTD. Project progress work #836 (Closed): Wiring and assembly equipment panel box
- - Wiring HMI Box
- Wiring Master control box - 10:55 ADVICS MANUFACTURING (THAILAND) CO., LTD. Project progress work #835 (Closed): EE Drawing deisgn
- - Make drawing diagram
- Part list
- Make PO