- 15:51 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #499 (Closed): [Coding] MT MOC Line IoT system for AH Brake)
- IoT system add function QR-Code Frist and Final process
- 15:49 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #499 (Closed): [Coding] MT MOC Line IoT system for AH Brake)
- Test Packing system and IoT system
- 15:48 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #499 (Closed): [Coding] MT MOC Line IoT system for AH Brake)
- Test Packing system and IoT system
- 15:48 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #499 (Closed): [Coding] MT MOC Line IoT system for AH Brake)
- Test Packing system
- 15:47 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #499 (Closed): [Coding] MT MOC Line IoT system for AH Brake)
- Test Packing system
- 15:47 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #499 (Closed): [Coding] MT MOC Line IoT system for AH Brake)
- Test Packing system
- 15:50 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #718 (In Progress): Machine operation monitoring for KAWASAKI)
- Meeting about pokayoke system
- 15:44 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #718 (In Progress): Machine operation monitoring for KAWASAKI)
- Meeting about pokayoke system
- 15:50 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #796 (Closed): [ Wring & Assembly ] Andon monitoring system Control cabinet 3 Set)
- Communication PLC Test
- 15:41 A.N.I. LOGISTICS, LTD. 8.00 hours (Project progress work #801 (Closed): EKD system phase 4)
- Access point installation