Project

General

Profile

Priroj Neamjarn's activity

From 02 Nov 2024 to 11 Nov 2024

11 Nov 2024

16:32 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
today
-Receive Finish Case (Handy)
tomorrow
-Receive Finish Case (Tablet)
-Move Finish Case (Handy)
Priroj Neamjarn

08 Nov 2024

16:37 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
today
-Receive Finish Case
tomorrow
-Receive Finish Case
Priroj Neamjarn

07 Nov 2024

16:46 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
today
-Receive Finish Case
-Lock screen
tomorrow
-Receive Finish Case
Priroj Neamjarn

06 Nov 2024

16:35 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
today
-Receive Finish Case
tomorrow
-Lock screen
-Receive Finish Case
Priroj Neamjarn

05 Nov 2024

16:31 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
today
-Outer Packing Process
tomorrow
-Lock screen
-Receive Finish Case
Priroj Neamjarn

04 Nov 2024

16:36 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
today
-Outer Packing Process
tomorrow
-Outer Packing Process
-Lock screen
-Receive Finish Case
Priroj Neamjarn

02 Nov 2024

16:42 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
today
-Outer Packing Process
tomorrow
-Outer Packing Process
-Lock screen
Priroj Neamjarn
 