Priroj Neamjarn's activity
From 02 Nov 2024 to 11 Nov 2024
11 Nov 2024
- 16:32 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Receive Finish Case (Handy)
tomorrow
-Receive Finish Case (Tablet)
-Move Finish Case (Handy)
08 Nov 2024
- 16:37 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Receive Finish Case
tomorrow
-Receive Finish Case
07 Nov 2024
- 16:46 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Receive Finish Case
-Lock screen
tomorrow
-Receive Finish Case
06 Nov 2024
- 16:35 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Receive Finish Case
tomorrow
-Lock screen
-Receive Finish Case
05 Nov 2024
- 16:31 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Outer Packing Process
tomorrow
-Lock screen
-Receive Finish Case
04 Nov 2024
- 16:36 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Outer Packing Process
tomorrow
-Outer Packing Process
-Lock screen
-Receive Finish Case
02 Nov 2024
- 16:42 A.N.I. LOGISTICS, LTD. Project progress work #739: [Development] CKD process system phase4
- today
-Outer Packing Process
tomorrow
-Outer Packing Process
-Lock screen
Also available in: Atom