04 Oct 2024

08:24 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 10.50 hours (Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project)
Support installation server pc rack Nattapong Sukcharoen

02 Oct 2024

16:25 AH BRAKE (THAILAND) CO., LTD. 8.00 hours (Project progress work #738 (Closed): [ Wring & Assembly ] Control cabinet)
Assembly Control Main PLC Nattapong Sukcharoen
16:22 AH BRAKE (THAILAND) CO., LTD. Project progress work #738 (Closed): [ Wring & Assembly ] Control cabinet
Wring & Assemble control Main master PLC , Packing Slave Box Nattapong Sukcharoen
16:14 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #737 (Closed): [ Installation & Support ] Installation and wiring andon project
- Support wiring lan cable
- Support installation server pc rack
Nattapong Sukcharoen
 