11 Sep 2024

13:45 A.N.I. LOGISTICS, LTD. 4.00 hours (Project progress work #131 (Closed): [Coding]Android handy and tablet modification Java)
Soraya Norasing
10:28 ASIAN STANLEY. INTERNATIONAL LIMITED. 4.00 hours (Project progress work #674 (Closed): [Installation]Process Control System phase2)
Fix slow data loading issues, fix API, test the system with customers. Soraya Norasing
10:27 TOMAS TECH CO., LTD. 4.00 hours (Project progress work #622 (In Progress): For internal meeting and other)
Internal meeting with K.Pai about ASI slow handy problem. Internal meeting with K.Nueng about YAMATO project Soraya Norasing

09 Sep 2024

16:44 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #593 (Closed): [Coding] Warehouse management system handyterminal Java)
Inbound Detail Soraya Norasing
16:44 YAMATO ELECTRIC (THAILAND) CO., LTD. 8.00 hours (Project progress work #593 (Closed): [Coding] Warehouse management system handyterminal Java)
Inbound schedule & Inbound Detail Soraya Norasing
16:40 YAMATO ELECTRIC (THAILAND) CO., LTD. 6.00 hours (Project progress work #593 (Closed): [Coding] Warehouse management system handyterminal Java)
Inbound schedule Soraya Norasing
 