- 17:30 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 5.00 hours (Project progress work #658 (Closed): Documents and design)
- Update spec document to version3
- 17:29 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 1.00 hour (Project progress work #658 (Closed): Documents and design)
- Preparing punchlist report rev1
- 00:50 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 2.00 hours (Project progress work #658 (Closed): Documents and design)
- Meeting with ERP at online #3
- 17:27 A.N.I. LOGISTICS, LTD. 2.00 hours (Project progress work #130 (Closed): [Coding]Inner packing screen function C#)
- Check and fix the incorrect data from racing condition problem on OUTER PACKING STEP3 of Handy
- 00:44 A.N.I. LOGISTICS, LTD. 2.00 hours (Project progress work #130 (Closed): [Coding]Inner packing screen function C#)
- Support and check the problem from user
- 00:56 NTPT COMPANY LIMITED. 4.00 hours (Project progress work #673 (In Progress): [Settings] Asprova implementation)
- Check more details regarding to new requirements from user
- 00:46 NTPT COMPANY LIMITED. 4.00 hours (Project progress work #673 (In Progress): [Settings] Asprova implementation)
- 00:46 NTPT COMPANY LIMITED. 4.00 hours (Project progress work #673 (In Progress): [Settings] Asprova implementation)
- Check master data
- 00:44 NTPT COMPANY LIMITED. 8.00 hours (Project progress work #673 (In Progress): [Settings] Asprova implementation)
- 00:48 ASUTO GLOBAL LOGISTICS (THAILAND) CO., LTD. 2.00 hours (Project progress work #623 (In Progress): [Installation] Install Raspi and TV monitor)
- Internal meeting about HT spec
- 00:41 TOMAS TECH CO., LTD. 1.00 hour (Project progress work #671 (In Progress): [Meeting] Interview and other)
- Interview
- 00:39 TOMAS TECH CO., LTD. Project progress work #671 (In Progress): [Meeting] Interview and other
- 00:39 TOMAS TECH CO., LTD. 1.00 hour (Project progress work #671 (In Progress): [Meeting] Interview and other)
- Meeting about work handover of K.Pam
- 00:34 TOMAS TECH CO., LTD. 2.00 hours (Project progress work #671 (In Progress): [Meeting] Interview and other)
- take photo and meeting at office
- 00:36 YAMATO ELECTRIC (THAILAND) CO., LTD. 2.00 hours (Project progress work #608 (Closed): [Documentation] Get requirements of project)
- Internal meeting about assign web
28 Aug 2024
- 14:09 A.N.I. LOGISTICS, LTD. 4.00 hours (Project progress work #130 (Closed): [Coding]Inner packing screen function C#)
- Modify DB trigger about user name and report
- 14:06 ACME INDUSTRY CO.,LTD. 5.00 hours (Project progress work #652 (Closed): System support and maintenance)
- Modify repack label function (cont.)
- 14:04 TOYOTA BOSHOKU FILTRATION SYSTEM (THAILAND) CO., LTD. 3.00 hours (Project progress work #658 (Closed): Documents and design)
- Meeting on-line #2
- 13:54 NTPT COMPANY LIMITED. 8.00 hours (Project progress work #673 (In Progress): [Settings] Asprova implementation)
- Try to generate the production schedule and check the item master
27 Aug 2024
- 09:30 YAMATO ELECTRIC (THAILAND) CO., LTD. 1.00 hour (Project progress work #608 (Closed): [Documentation] Get requirements of project)
- Update spec and punchlist report
- 09:28 YAMATO ELECTRIC (THAILAND) CO., LTD. 3.00 hours (Project progress work #608 (Closed): [Documentation] Get requirements of project)
- 09:26 TOMAS TECH CO., LTD. 8.00 hours (Project progress work #671 (In Progress): [Meeting] Interview and other)
- 09:26 TOMAS TECH CO., LTD. Project progress work #646 (In Progress): WDT and smartwatch demo project
- 09:23 DAIFUKU (THAILAND) LTD. Project progress work #701 (Close request): [Area3] Site survey