15 Jun 2024

14:00 DENSO PHILIPPINES CORPORATION 0.00 hour (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
Soraya Norasing
12:00 ASIAN STANLEY. INTERNATIONAL LIMITED. 4.00 hours (Project progress work #465 (Closed): [Coding]ASI - Process Control System Phase2 -Java)
meeting with customer and modify spec R5 Soraya Norasing
12:00 A.N.I. LOGISTICS, LTD. 4.00 hours (Project progress work #131 (Closed): [Coding]Android handy and tablet modification Java)
fixed problem model PBP scan SCAN_STEP3_SUCCESS can't responce and test with K.nack Soraya Norasing

13 Jun 2024

15:53 A.N.I. LOGISTICS, LTD. 3.00 hours (Project progress work #131 (Closed): [Coding]Android handy and tablet modification Java)
Soraya Norasing
15:50 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #465 (Closed): [Coding]ASI - Process Control System Phase2 -Java)
Modify Specifications Documentation R4 and design database Soraya Norasing

11 Jun 2024

22:38 A.N.I. LOGISTICS, LTD. 5.00 hours (Project progress work #131 (Closed): [Coding]Android handy and tablet modification Java)
Soraya Norasing
22:37 DENSO PHILIPPINES CORPORATION 2.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
Soraya Norasing
22:35 TOMAS TECH CO., LTD. 1.00 hour (Project progress work #622 (In Progress): For internal meeting and other)
Soraya Norasing

10 Jun 2024

22:04 TOMAS TECH CO., LTD. 2.00 hours (Project progress work #622 (In Progress): For internal meeting and other)
internal meeting with K.nack about found bug on handy app and Request advice about ASI phase2 project Soraya Norasing
22:01 ASIAN STANLEY. INTERNATIONAL LIMITED. 6.00 hours (Project progress work #465 (Closed): [Coding]ASI - Process Control System Phase2 -Java)