Soraya Norasing's activity
From 30 May 2024 to 08 Jun 2024
08 Jun 2024
- 23:11 NTPT COMPANY LIMITED. 4.00 hours (Project progress work #504 (Closed): [Setting] Production planning system APS 500,000 work)
- Study the use of the Asprova program.(video clip)
- 22:50 NTPT COMPANY LIMITED. 8.00 hours (Project progress work #504 (Closed): [Setting] Production planning system APS 500,000 work)
- Study the Aspova program manual. (Bacis) Learn about tables and data collection.
- 22:49 NTPT COMPANY LIMITED. 8.00 hours (Project progress work #504 (Closed): [Setting] Production planning system APS 500,000 work)
- Study the Aspova program manual. meeting with customer at factory
- 23:02 ASIAN STANLEY. INTERNATIONAL LIMITED. 8.00 hours (Project progress work #465 (Closed): [Coding]ASI - Process Control System Phase2 -Java)
- Modify Specifications Documentation R3 and design database
- 23:00 ASIAN STANLEY. INTERNATIONAL LIMITED. 2.00 hours (Project progress work #465 (Closed): [Coding]ASI - Process Control System Phase2 -Java)
- meeting with customer about report phase2 and Help customers find the cause and solve the problem of not being able t...
- 22:58 A.N.I. LOGISTICS, LTD. 4.00 hours (Project progress work #131 (Closed): [Coding]Android handy and tablet modification Java)
- Modify application on tablet change column MAT to Receive
- 22:56 TOMAS TECH CO., LTD. 2.00 hours (Project progress work #622 (In Progress): For internal meeting and other)
- Orientation new member
- 22:52 TOMAS TECH CO., LTD. 4.00 hours (Project progress work #622 (In Progress): For internal meeting and other)
- Internal with K.Ryo about Asprova, Internal meeting with K.Pai about pagasus and MAST handy application
- 22:54 DENSO PHILIPPINES CORPORATION 4.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- test & modify smart watch system with K.nack (Add ACCEPTED_NOTIFY command)
03 Jun 2024
- 23:29 NTPT COMPANY LIMITED. 8.00 hours (Project progress work #504 (Closed): [Setting] Production planning system APS 500,000 work)
- Design document forms and Study the use of the Esprova program.
- 23:27 NTPT COMPANY LIMITED. 8.00 hours (Project progress work #504 (Closed): [Setting] Production planning system APS 500,000 work)
- Modify Specifications Documentation R3 and Design document form
- 23:26 NTPT COMPANY LIMITED. 8.00 hours (Project progress work #504 (Closed): [Setting] Production planning system APS 500,000 work)
- View documents, contact, request an explanation with the customer. and design forms
- 23:23 ASIAN STANLEY. INTERNATIONAL LIMITED. 4.00 hours (Project progress work #465 (Closed): [Coding]ASI - Process Control System Phase2 -Java)
- Meeting with customer
- 23:22 ASIAN STANLEY. INTERNATIONAL LIMITED. 7.00 hours (Project progress work #465 (Closed): [Coding]ASI - Process Control System Phase2 -Java)
- Modify Specifications Documentation R2
- 23:19 TOMAS TECH CO., LTD. 1.00 hour (Project progress work #622 (In Progress): For internal meeting and other)
- NSET meeting RFID weight check function
- 23:17 TOMAS TECH CO., LTD. 2.00 hours (Project progress work #622 (In Progress): For internal meeting and other)
- meeting with K.poo Minebea about explains how to set up the printer's pot.
- 23:13 THAI METALTECH CO., LTD. 4.00 hours (Project progress work #621 (Closed): Meeting)
- Internal meeting about specification Thai Matal Tech
- 22:40 DENSO PHILIPPINES CORPORATION 2.00 hours (Project progress work #112 (Closed): [Coding]Android smart watch , smart phone , Data linkage function Phase01)
- meetting with customer about Problem with app not being able to launch after preset.
Also available in: Atom