05 Mar 2024

21:52 THAI NIPPON FOODS CO., LTD. 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
On-site installation Nattapol Poeam
21:51 THAI NIPPON FOODS CO., LTD. 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
On-site installation Nattapol Poeam
21:49 ADVICS MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #436 (Closed): [ On-site ] Installation shipping traceability system)
On-site installation update program order list and handy Nattapol Poeam

02 Mar 2024

09:25 THAI NIPPON FOODS CO., LTD. 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
Install and uninstall EP02 for setting IP Address Nattapol Poeam

29 Feb 2024

20:33 THAI NIPPON FOODS CO., LTD. 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
Install IoT system and check signal from machine Nattapol Poeam
20:33 THAI NIPPON FOODS CO., LTD. 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
Install IoT system and check signal from machine Nattapol Poeam
20:33 THAI NIPPON FOODS CO., LTD. 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
Install IoT system and check signal from machine Nattapol Poeam
 