Nattapol Poeam's activity
From 05 Feb 2024 to 14 Feb 2024
14 Feb 2024
- 22:40 MATSUMOTO KOSAN (THAILAND) CO., LTD. Sales support #435 (Confirmation request): Meeting and site survey about collect data from Machine CNC
- 22:39 TOMAS TECH CO., LTD. Project progress work #433 (Confirmation request): ASI online training safety
- 22:33 ISUZU ENGINE MANUFACTURING CO., (THAILAND) LTD. Project progress work #402: Modification program for record S/N to CF-Card
- [ To day ]
- Backup data from CF-Card to check Error
[ Next action ]
- Report to K.Papol about result form file re... - 22:33 ISUZU ENGINE MANUFACTURING CO., (THAILAND) LTD. 1.00 hour (Project progress work #402 (Closed): Modification program for record S/N to CF-Card)
- Backup data record
- 22:31 ISUZU ENGINE MANUFACTURING CO., (THAILAND) LTD. Project progress work #402 (In Progress): Modification program for record S/N to CF-Card
- 22:31 ADVICS MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #436 (Closed): [ On-site ] Installation shipping traceability system)
- Install and test functon
- 22:30 ADVICS MANUFACTURING (THAILAND) CO., LTD. Project progress work #436: [ On-site ] Installation shipping traceability system
- [ To day ]
- Test information check
[ Next acction ]
- Make program generate QR-Code from data gateway ( K.Kamol )... - 22:30 ADVICS MANUFACTURING (THAILAND) CO., LTD. 4.00 hours (Project progress work #436 (Closed): [ On-site ] Installation shipping traceability system)
- Test system
- 22:27 MITSUBISHI HEAVY INDUSTRIES-MAHAJAK AIR CONDITIONERS CO., LTD. 3.00 hours (Project progress work #211 (Closed): MACO monitor robot in production line IoT project)
- Meeting about update requiment of custumer
12 Feb 2024
- 22:09 ADVICS MANUFACTURING (THAILAND) CO., LTD. Project progress work #436 (In Progress): [ On-site ] Installation shipping traceability system
- [ To day ]
- Config AP
- Config Handy
- Wiring Power supply 24V to AP
[ Next Action ]
- Install AP
- Change DB
... - 22:09 ADVICS MANUFACTURING (THAILAND) CO., LTD. 8.00 hours (Project progress work #436 (Closed): [ On-site ] Installation shipping traceability system)
- Installation at site MOC line
- 22:06 ADVICS MANUFACTURING (THAILAND) CO., LTD. Project progress work #436 (Closed): [ On-site ] Installation shipping traceability system
- Installation program
- Handy
- PC Packing
Installtion AP
- Final line MOC
Data base
- Change local DB to Server - 22:03 THAI NIPPON FOODS CO., LTD. 4.00 hours (Project progress work #434 (Closed): [ Specicication and document ] for Water treatment project)
- Find equipment and compare price
- 22:02 MATSUMOTO KOSAN (THAILAND) CO., LTD. Sales support #435 (In Progress): Meeting and site survey about collect data from Machine CNC
- 22:01 MATSUMOTO KOSAN (THAILAND) CO., LTD. 4.00 hours (Sales support #435 (Closed): Meeting and site survey about collect data from Machine CNC)
- Site survey and meeting
- 22:01 MATSUMOTO KOSAN (THAILAND) CO., LTD. Sales support #435 (Closed): Meeting and site survey about collect data from Machine CNC
- [ Site survey ]
- Wiring Lan system
- Machine
- MT-Link system
[ Next Acction ]
- Make estimate cost
08 Feb 2024
- 15:42 THAI NIPPON FOODS CO., LTD. Project progress work #434 (In Progress): [ Specicication and document ] for Water treatment project
- 15:42 THAI NIPPON FOODS CO., LTD. Project progress work #434: [ Specicication and document ] for Water treatment project
- [ Next Acction ]
Site survey 11/02/24
- Expain concept and point installation sensor to SND Team.
- Water flow met... - 15:42 THAI NIPPON FOODS CO., LTD. 4.00 hours (Project progress work #434 (Closed): [ Specicication and document ] for Water treatment project)
- Schedule and Sub Schedule
- 15:34 THAI NIPPON FOODS CO., LTD. Project progress work #434 (Closed): [ Specicication and document ] for Water treatment project
- - Schedule
- Sub Schedule
- Specification
- Data document - 10:34 TOMAS TECH CO., LTD. 4.00 hours (Project progress work #433 (Closed): ASI online training safety )
- Online training safety
- 10:33 TOMAS TECH CO., LTD. Project progress work #433 (Closed): ASI online training safety
- Training safety
07 Feb 2024
- 22:28 THAI NIPPON FOODS CO., LTD. Project progress work #87: IoT Equipment for machine operation project
- [ To day ]
- Re check data memory for addition alarm history
- Revised alarm design for all machine
- Check data m... - 22:28 THAI NIPPON FOODS CO., LTD. 8.00 hours (Project progress work #87 (Closed): IoT Equipment for machine operation project)
- Revised data memory
06 Feb 2024
- 16:48 MITSUBISHI HEAVY INDUSTRIES-MAHAJAK AIR CONDITIONERS CO., LTD. Sales support #430 (Closed): Meeting about update requirment of project
- [ Meeting ]
- Update requiment of project
- Update schedule of project - 16:46 MITSUBISHI HEAVY INDUSTRIES-MAHAJAK AIR CONDITIONERS CO., LTD. Sales support #429 (Closed): Meeting about update requirment of project
- [ Meeting ]
- Update requirment of project
- Update schedule of project - 16:33 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #119: [Internal Design] DB and various functions, man-hour calculation
- [ Task ]
- Test function PLC Link beeteen Fac1 to Fac3 - 16:33 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. 8.00 hours (Project progress work #119 (Closed): [Internal Design] DB and various functions, man-hour calculation)
- Function PLC Data link
- 16:29 THAI NIPPON FOODS CO., LTD. 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Power on TB-Box Plant A and Data monitor from Machine Spiral
- 16:27 THAI NIPPON FOODS CO., LTD. 8.00 hours (Project progress work #126 (Closed): [Installation&On-site support] Production IoT system for TNF)
- Monitoring and communication test on Plant A
Also available in: Atom