Nattapol Poeam's activity
From 26 Jan 2024 to 04 Feb 2024
02 Feb 2024
- 16:56 KEYENCE (THAILAND) CO., LTD. Project progress work #427 (In Progress): [ Support and install program ] for demo-kit WD
- Next Action >> Wait Custumer confrim date delivery
- 16:55 KEYENCE (THAILAND) CO., LTD. Project progress work #427 (Closed): [ Support and install program ] for demo-kit WD
- Demo-kit WD
31 Jan 2024
- 20:07 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #405: [Requirement definition] Infrastructure IoT system for Jtekt Automotive
- - Expain concept to SND Team
- Expain concept master control design to K.Suchin
- Reserch data about Powermeter and CT - 19:35 DAIFUKU (THAILAND) LTD. Sales support #415 (In Progress): [Requirement and support] Installation camera Area 1-3
- 19:33 DAIFUKU (THAILAND) LTD. Sales support #415 (Closed): [Requirement and support] Installation camera Area 1-3
- Installation camera area 1-3
- 10:38 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #413 (Closed): [Installation&On-site support] Software installation for Infrastructure IoT Project
- - Installation program
- Connect device powermeter,Air flow sensor,Chiller system - 10:34 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #412 (Closed): [Installation&On-site support] Hardware installation for Infrastructure IoT Project
- - Installation powermeter
- Installation Air flow sensor
- Installation and connect to chiller system - 10:26 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #411 (Closed): [ Task ] Drawing design for Master control box
- - Master control box design
- 10:16 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #410 (Closed): [ Task ] Program and Dashboard Development
- [ Task ]
- Program design
- Dashboard design
- Data report design
- Other function design - 10:10 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #409 (Closed): [Installation&On-site support] Production IoT system for JATH
- Installation IoT system for final line
- 10:03 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #408 (Closed): [Installation&On-site support] Production IoT system for JATH
- Installation IoT for Final line Project
- 10:01 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #407 (Closed): [Installation&On-site support] Production IoT system for JATH
- Installation IoT System
- 08:06 THAI NIPPON FOODS CO., LTD. Project progress work #403 (In Progress): Summarize equipment of Water treatment project
30 Jan 2024
- 21:31 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #405 (In Progress): [Requirement definition] Infrastructure IoT system for Jtekt Automotive
- 21:27 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #405 (Closed): [Requirement definition] Infrastructure IoT system for Jtekt Automotive
- Infrastructure IoT Project
- Kick off meeting
- Site servey
Next action
- Make drawing diagram of Control box mas... - 21:30 DAIFUKU (THAILAND) LTD. Project progress work #406 (In Progress): Prepare equipment for installation for Area1
- 21:29 DAIFUKU (THAILAND) LTD. Project progress work #406 (Closed): Prepare equipment for installation for Area1
- Prepare equipment for installation Area 1-3
- 21:17 TOMAS TECH CO., LTD. Sales support #404 (In Progress): OTICS (Thailand) Company Limited meeting about IoT system and site servey
- 21:15 TOMAS TECH CO., LTD. Sales support #404 (In Progress): OTICS (Thailand) Company Limited meeting about IoT system and site servey
- Site survey
- MDB and panel control point
Next acction
- Make concept and summarize equipment - 21:10 TOMAS TECH CO., LTD. Project progress work #398 (Confirmation request): Make concept and summarize equipment for Interlock system prohect
- 20:18 TOMAS TECH CO., LTD. Project progress work #398 (Closed): Make concept and summarize equipment for Interlock system prohect
- - Make and summarize concept.
- Summarize equipment. - 21:07 THAI NIPPON FOODS CO., LTD. Project progress work #403 (Closed): Summarize equipment of Water treatment project
- summarize equipment
- 21:04 THAI NIPPON FOODS CO., LTD. Sales support #86 (In Progress): IoT Equipment for Water treatment project
- 21:00 ISUZU ENGINE MANUFACTURING CO., (THAILAND) LTD. Project progress work #402 (Closed): Modification program for record S/N to CF-Card
- [ Task ]
- Add program for record data to cf-card
- Config camera SRX-300 - 20:52 TOMAS TECH CO., LTD. Sales support #269: Automation for receiving and shipping of Fabrinet
- Concept design
1. Received
2. Shipping - 20:48 JTEKT AUTOMOTIVE (THAILAND) CO.,LTD. Project progress work #328 (Confirmation request): Crate IoT data collection box for JATH
- 20:45 TOMAS TECH CO., LTD. Sales support #312 (Confirmation request): Fanuc traning and appointment Fanuc staff
- 20:39 ISUZU ENGINE MANUFACTURING CO., (THAILAND) LTD. Project progress work #401 (Confirmation request): Site survey for confrim location display
- 20:38 ISUZU ENGINE MANUFACTURING CO., (THAILAND) LTD. Project progress work #401 (Closed): Site survey for confrim location display
- Confrim scope work and location display
- 20:34 THAI NIPPON FOODS CO., LTD. Project progress work #400 (Closed): Program developer and Dashboard design
- Program developer and Dashboard design
- 20:30 THAI NIPPON FOODS CO., LTD. Project progress work #399 (Closed): [Installation&On-site support] Production IoT system for TNF
- Installation IoT sytem for Machine operation monitoring system project
- 20:26 THAI NIPPON FOODS CO., LTD. Sales support #175 (Confirmation request): EV charger installation project
- 20:24 THAI NIPPON FOODS CO., LTD. Project progress work #201 (Confirmation request): Summary of all equipment for use in the Machine operation monitoring systems project.
- 20:23 BIG STAR CO., LTD. Sales support #209 (Confirmation request): Shoe size sorting machine project Concept proposal
- 20:03 ATA CASTING TECHNOLOGY CO., LTD. Problem-Bug #215 (Confirmation request): Request verification of the data collection of machine
Also available in: Atom