27 Dec 2023

17:42 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #97 (Closed): [Coding]Android handyterminal BTA500)
Soraya Norasing

26 Dec 2023

22:42 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #97 (Closed): [Coding]Android handyterminal BTA500)
Soraya Norasing

25 Dec 2023

22:19 ASIAN STANLEY. INTERNATIONAL LIMITED. 2.00 hours (Project progress work #342 (Closed): Found a problem, unable to issue a report.)
Soraya Norasing
22:11 MINEBEA ACCESSSOLUTIONS THAI LTD. 6.00 hours (Project progress work #97 (Closed): [Coding]Android handyterminal BTA500)
Soraya Norasing
22:11 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #97 (Closed): [Coding]Android handyterminal BTA500)
edit code inbound detail page and coding label schedule Soraya Norasing

22 Dec 2023

22:17 MINEBEA ACCESSSOLUTIONS THAI LTD. 8.00 hours (Project progress work #97 (Closed): [Coding]Android handyterminal BTA500)
Soraya Norasing
22:16 MINEBEA ACCESSSOLUTIONS THAI LTD. 6.00 hours (Project progress work #97 (Closed): [Coding]Android handyterminal BTA500)
coding inbound detail page Soraya Norasing
19:07 ASIAN STANLEY. INTERNATIONAL LIMITED. 0.00 hour (Project progress work #325 (Closed): Test the report)
Soraya Norasing
16:06 ASIAN STANLEY. INTERNATIONAL LIMITED. 2.00 hours (Project progress work #325 (Closed): Test the report)
test report with customer and instaill plcc line Soraya Norasing
16:05 A.N.I. LOGISTICS, LTD. 0.00 hour (Problem-Bug #253 (Closed): Found a problem of not being able to use the tablet when the internet was down.)
Soraya Norasing
 