Project

General

Profile

Kittisak Isarapongporn's activity

From 18 Nov 2023 to 27 Nov 2023

24 Nov 2023

17:07 ACME INDUSTRY CO.,LTD. 8.00 hours (Project progress work #52 (Closed): Issue topics)
Kittisak Isarapongporn

23 Nov 2023

16:55 MINEBEA ACCESSSOLUTIONS THAI LTD. 4.00 hours (Project progress work #96 (Closed): [Internal Design] DB and various functions, man-hour calculation)
DB Design and confirm the label spec detail Kittisak Isarapongporn
16:46 A.N.I. LOGISTICS, LTD. 4.00 hours (Project progress work #226 (Closed): CKD project requirement and document preparation)
Meeting and prepare document Kittisak Isarapongporn

22 Nov 2023

16:46 A.N.I. LOGISTICS, LTD. 4.00 hours (Project progress work #226 (Closed): CKD project requirement and document preparation)
Modify the spec revision 3 and update the TODO list Kittisak Isarapongporn
16:45 MINEBEA ACCESSSOLUTIONS THAI LTD. 4.00 hours (Project progress work #96 (Closed): [Internal Design] DB and various functions, man-hour calculation)
DB Design and confirm the outbound spec detail Kittisak Isarapongporn

21 Nov 2023

17:20 ACME INDUSTRY CO.,LTD. 4.00 hours (Project progress work #52 (Closed): Issue topics)
Integrate and test the BT print function Kittisak Isarapongporn
17:15 ACME INDUSTRY CO.,LTD. 5.00 hours (Project progress work #204 (Closed): UAT about the WMS system and onsite support)
UAT and teaching Kittisak Isarapongporn
17:14 A.N.I. LOGISTICS, LTD. 4.00 hours (Project progress work #226 (Closed): CKD project requirement and document preparation)
Modify the spec from the last meeting and prepare the data for tomorrow meeting. Kittisak Isarapongporn
17:10 MINEBEA ACCESSSOLUTIONS THAI LTD. 4.00 hours (Project progress work #96 (Closed): [Internal Design] DB and various functions, man-hour calculation)
Hold the meeting about the spec confirm and assign the job to dev team Kittisak Isarapongporn

18 Nov 2023

17:57 ACME INDUSTRY CO.,LTD. 4.00 hours (Project progress work #51 (Closed): Overall project development for web and handy)
Add the unconfirm function to Inbound inquiry report (Revoke the confirm by QC) Kittisak Isarapongporn
17:56 MINEBEA ACCESSSOLUTIONS THAI LTD. 4.00 hours (Project progress work #96 (Closed): [Internal Design] DB and various functions, man-hour calculation)
Spec confirmation with k.Ryo and meeting about the handy functions, will hold the meeting to update to K.So again on ... Kittisak Isarapongporn
 