Project

General

Profile

Kittisak Isarapongporn's activity

From 08 Nov 2023 to 17 Nov 2023

17 Nov 2023

16:40 ACME INDUSTRY CO.,LTD. 4.00 hours (Project progress work #52 (Closed): Issue topics)
Fix the store procedure to support to create the schedule with minimum outbound qty Kittisak Isarapongporn
16:38 ACME INDUSTRY CO.,LTD. 4.00 hours (Project progress work #52 (Closed): Issue topics)
Show outsource information in schedule / check and fix the schedule generate related with outsource BOM Kittisak Isarapongporn

16 Nov 2023

16:52 ACME INDUSTRY CO.,LTD. 8.00 hours (Project progress work #51 (Closed): Overall project development for web and handy)
Create OUTSOURCE information to remark / Cancel the confirmation by QC staff Kittisak Isarapongporn

15 Nov 2023

17:35 ACME INDUSTRY CO.,LTD. 4.00 hours (Project progress work #52 (Closed): Issue topics)
Test and fix bug Kittisak Isarapongporn
16:29 ACME INDUSTRY CO.,LTD. 4.00 hours (Project progress work #176 (Closed): SATO label print via Bluetooth)
Kittisak Isarapongporn
15:19 A.N.I. LOGISTICS, LTD. 2.00 hours (Project progress work #226 (Closed): CKD project requirement and document preparation)
Kittisak Isarapongporn
15:19 A.N.I. LOGISTICS, LTD. 2.00 hours (Project progress work #226 (Closed): CKD project requirement and document preparation)
Meeting at online Kittisak Isarapongporn

14 Nov 2023

16:58 A.N.I. LOGISTICS, LTD. 4.00 hours (Project progress work #226 (Closed): CKD project requirement and document preparation)
Create the TO-DO list and modify the specification revision 2 Kittisak Isarapongporn
16:54 ACME INDUSTRY CO.,LTD. 4.00 hours (Project progress work #176 (Closed): SATO label print via Bluetooth)
Test and develop the print BT function Kittisak Isarapongporn

13 Nov 2023

17:30 ACME INDUSTRY CO.,LTD. 3.00 hours (Project progress work #176 (Closed): SATO label print via Bluetooth)
Studying and test the example source code from SATO dev team Kittisak Isarapongporn
17:27 ACME INDUSTRY CO.,LTD. 5.00 hours (Project progress work #204 (Closed): UAT about the WMS system and onsite support)
Teaching about schedule operation for part control, press, kashime and QC Kittisak Isarapongporn

10 Nov 2023

16:53 A.N.I. LOGISTICS, LTD. 4.00 hours (Problem-Bug #221 (Closed): Found the problem with the handy show "Schedule not found")
Finding the problem causes Kittisak Isarapongporn

09 Nov 2023

17:15 ACME INDUSTRY CO.,LTD. 4.00 hours (Project progress work #163 (Closed): Import BOM/Modify script to manage uncontrol items and outsource details)
Import BOM Kittisak Isarapongporn
17:10 A.N.I. LOGISTICS, LTD. 4.00 hours (Problem-Bug #214 (Closed): Found the problem with the handy being able to scan the other label [STAGING AREA])
Adjust the code and testing Kittisak Isarapongporn

08 Nov 2023

22:51 A.N.I. LOGISTICS, LTD. 4.00 hours (Problem-Bug #214 (Closed): Found the problem with the handy being able to scan the other label [STAGING AREA])
Investigate and analyze the instructions to resolve the problem Kittisak Isarapongporn
21:40 A.N.I. LOGISTICS, LTD. 4.00 hours (Sales support #179 (Closed): Join the meeting at on-site)
Kittisak Isarapongporn
 

Also available in: Atom