Yutthapong Sricha's activity
From 05 Nov 2023 to 14 Nov 2023
13 Nov 2023
- 16:54 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
- config remote ebisu and clen database Master
10 Nov 2023
- 16:49 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
- Test API ItemMaster , Supplier , Customer , recheck convert qty unit
09 Nov 2023
- 17:51 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
- 17:50 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
07 Nov 2023
- 17:23 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
- 17:00 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
- 16:59 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
- 16:45 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
- 16:38 EBISU FOODS CO., LTD. 5.00 hours (Project progress work #16 (Closed): WMS Web Development )
- 16:32 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
- 16:24 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
- 16:18 EBISU FOODS CO., LTD. 8.00 hours (Project progress work #16 (Closed): WMS Web Development )
- Web Pegasus Tag Label generator (continus yesterday) and change Design Label / Test Inbound Inquiry Report / update ...
- 16:15 EBISU FOODS CO., LTD. 4.00 hours (Project progress work #16 (Closed): WMS Web Development )
- Web pegasus Production Schedule / Tag Label generator
- 17:03 ASIAN STANLEY. INTERNATIONAL LIMITED. 2.00 hours (Problem-Bug #73 (Closed): Found 500 return error)
- Monitor web error by anydesk
- 17:03 ASIAN STANLEY. INTERNATIONAL LIMITED. 2.00 hours (Problem-Bug #73 (Closed): Found 500 return error)
- Monitor web error by anydesk
- 17:02 ASIAN STANLEY. INTERNATIONAL LIMITED. 2.00 hours (Problem-Bug #73 (Closed): Found 500 return error)
- Monitor web error by anydesk
- 16:42 SANKO MOLD AND PLASTICS (THAILAND) COMPANY LIMITED. 4.00 hours (Project progress work #50 (Closed): Add delete function)
- 16:41 SANKO MOLD AND PLASTICS (THAILAND) COMPANY LIMITED. 8.00 hours (Project progress work #50 (Closed): Add delete function)
- 16:41 SANKO MOLD AND PLASTICS (THAILAND) COMPANY LIMITED. 8.00 hours (Project progress work #50 (Closed): Add delete function)
- 16:11 ASIAN STANLEY. INTERNATIONAL LIMITED. 4.00 hours (Project progress work #205 (Closed): Change Web Screen 2 On TV )
- Change condition in function on web site show on TV screen 2